The project and the faulty columns
Tung Chung West is one of two new stations on the HK$24.2 billion Tung Chung line extension, which began construction in May 2023 with completion targeted in 2029. The station will connect to the existing Tung Chung station via a 1.3-kilometer tunnel, serving residents of Yat Tung, Mun Tung and nearby developments; the project also includes Tung Chung East station. The defects emerged as follows:
- In early October, the registered structural engineer’s supervisory team spotted the first defective column and told the contractor to fix it.
- On October 27, the Buildings Department confirmed two defective columns during an inspection and ordered a full investigation and prompt rectification.
- As formwork was removed, more defects emerged; by November 6, about 30 affected columns had been identified.
In addition, the MTR said its October inspections found a subcontractor had used patching materials at column heads without approval, prompting it to suspend the work and investigate. The structural engineer must report to the Buildings Department by mid-November; the MTR must report to the Highways Department within two weeks of notifying it on November 2; and main contractor Bouygues-Dragages Joint Venture must submit a report and rectification plan.