One queue, competing explanations
On November 4, The Star reported serious congestion on roads leading to the Bangunan Sultan Iskandar immigration complex in Johor Bahru. Its account described a major power outage on the Singapore side beginning around noon, although the Malaysian checkpoint’s counters were reportedly functioning. A broken lorry was also mentioned as an additional problem. The resulting queues were real, but the explanation of their origin was disputed.
Responding to The Straits Times the following day, ICA categorically rejected a power outage at Woodlands Checkpoint. It explained that scheduled electrical maintenance ran from 10 a.m. to 2 p.m. at Old Woodlands Checkpoint. That facility temporarily stopped clearing arriving lorries, while lorry processing continued at the main Woodlands Checkpoint. The distinction is important: a planned restriction at one facility is not evidence of an uncontrolled blackout across the crossing.
The breakdowns that prolonged the delays
ICA said operations at the older facility resumed around 4 p.m. Two lorries then broke down on the Malaysian stretch of the Causeway toward Singapore, at approximately 4:30 p.m.