What the satellite images reveal
US satellite company Planet Labs photographed the al-Duwadimi complex between April 2025 and September 2026. Researchers Sam Lair and Michael Duitsman of FPRI, a non-partisan research organisation based in Philadelphia, identified a new building housing casting pits, where a mixture of fuel ingredients is poured into missile motor casings and left to harden. The building is at least twice as large as the existing facility and flanked by blast walls, while a second new building could be used to store ingredients or finished missile components.
According to the FPRI assessment, construction unfolded in the following stages:
- April 2025: ground-clearing and digging for the suspected storage building
- Late April or early May 2025: work begins on the suspected casting-pit building
- December 12, 2025: images show two deep pits inside the still roofless building
- September 18, 2026: the roof is still unfinished, with heavy-duty blast-diverting walls on either side
The researchers say finishing the roof would not take long, but installing casting equipment may take several months, and the facility could start producing missiles as early as year-end. The Saudi embassy and the country's Information Ministry did not respond to requests for comment.