MAIN STORY
A programme of 527 escalators, not 527 simultaneous closures
The November 19 statement from LTA and the two rail operators breaks the project into two groups: 290 escalators on the North-South, East-West and North East lines, and a further 237 on the Circle Line. The combined total is 527, but the number should not be mistaken for a simultaneous shutdown. Some affected escalators sit alongside stations, including pedestrian overhead bridges used beyond the ticket gates.
The first refurbishment works are scheduled to start on December 17, 2026. The stated 2032 completion target applies to the initial group of 290; a starting date for the Circle Line stage has yet to be announced. The first group also includes 83 units that were not due for upgrading during the earlier programme. By staggering activity, operators aim to avoid removing too many passenger routes at the same time.
Renewing the machinery and the passenger experience
Each escalator will take roughly four to five months to refurbish. The work involves motors, control systems, steps, handrails and safety components rather than merely cosmetic changes.