Two bidders at the midnight deadline
The tender closed at midnight on November 8 with fewer contenders than the government had hoped for. The commissioners will now examine whether the two offers are complete and comply with the tender's requirements. It is the third attempt to sell the group, after processes that closed in January and September 2025 failed to produce a sale.
Arvedi's appearance was the surprise. The Cremona-based group had not stood on its own in earlier rounds. A person close to the matter said its bid envisages a first electric arc furnace within two to three years, followed by a second and, subject to local approval, a direct reduced iron plant using its proprietary technology, with steel produced from raw material along a 180-metre line and far lower carbon emissions.
Jindal is a familiar suitor. Its earlier plan foresaw an electric furnace at Taranto of about 2 million tonnes and the import of 4 million tonnes of slabs from Oman, though Italian media reported that it was being revised after the court's decision. The steel federation Federacciai did not submit an offer, and US investor Flacks Group had said it would not bid without at least €1 billion in state support.
Steel without blast furnaces
The bids must contend with a plant transformed. The Court of Cassation upheld a Milan appeals court order to stop hot-end production, calling that ruling correct and reasonable, and the shutdown of coke ovens, blast furnaces and related units has since begun.