A key contract cancelled
In 2023, VAC signed a long-term deal with GM to supply permanent magnets for its electric vehicles from a new plant in South Carolina. At the time, VAC said the plant would support GM for a minimum of 10 years and supply a wide range of models.
In filings last week, Energy Fuels said a customer of the plant terminated its supply agreement on July 1, and VAC launched arbitration proceedings several days later. The filings did not name the customer, but GM reported this week that a supplier of a component for EV traction motors had initiated arbitration seeking damages after GM terminated a strategic sourcing agreement, without giving a reason.
A person familiar with the matter confirmed GM was the customer that cancelled the contract with e-VAC Magnetics. Both GM and Energy Fuels declined to comment because the arbitration is confidential. According to the filings, the dispute first arose in April 2026.
A $500 million plant put to the test
VAC’s plant in Sumter, South Carolina, went from a soybean field to magnet production in less than 20 months and was billed as the first large-scale producer of rare-earth magnets in the United States in more than a quarter century. At the opening ceremony, CEO Erik Eschen stressed the project’s strategic importance.