MAIN ARTICLE
A fixed nine-day gap in the timetable
Network Rail’s November 10 announcement sets the closure from Saturday, February 13, through Sunday, February 21, 2027, inclusive. Trains cannot use the route linking Three Bridges with Brighton, Hove or Lewes through Haywards Heath. Importantly, this does not mean every rail journey between London and Brighton disappears: a diverted direct service is planned, although it will take longer and will serve different intermediate stops.
Services operated by Thameslink, Southern and Gatwick Express will be affected. Trains on the main corridor towards London, Bedford and Cambridge will start or terminate at Three Bridges. Timetables on other Brighton routes, including East Coastway and West Coastway services, will also change. Direct trains between London and Gatwick Airport remain available, distinct from the closed tracks farther south.
How passengers can travel instead
Replacement buses are planned from Three Bridges through intermediate stations to Brighton; from Three Bridges to Lewes through Haywards Heath and Cooksbridge; from Three Bridges to Haywards Heath; between Haywards Heath and Plumpton; and between Lewes and East Grinstead on weekdays. Anyone changing with luggage, children or accessibility needs should allow extra time and examine the specific arrangements before leaving home.