A Double Squeeze: Weakening Credit And Local Opposition
According to the Financial Times, banks are now forced to hold more Oracle-linked project debt on their balance sheets than initially planned, as long-term investors have been reluctant to take on the risk. Oracle's corporate credit rating sits just one notch above junk following a downgrade by S&P in July. Notably, the development coincides with growing opposition from local residents to Project Jupiter over concerns about its impact on water supply and air quality, a factor that could disrupt construction of the massive AI infrastructure campus. Oracle, Santander and Jefferies did not respond to Reuters' requests for comment.
The Power Question Behind Project Jupiter
The Jupiter campus was initially expected to be powered by 2.2 gigawatts of gas turbines, but New Mexico's state land office has blocked a request to run a natural gas pipeline to the data center. That uncertainty over power infrastructure, combined with financial pressure from the debt, could complicate efforts to complete the campus as planned.