A rural proposal becomes an international test
Western Downs Digital Park is planned for farmland roughly 250 kilometres west of Brisbane. Its proposed computing load could reach 1.44 gigawatts, potentially making it one of Australia's largest data-centre developments. That figure describes the planned scale, not electricity already being consumed or a guarantee that the entire complex will operate at once.
The filing recorded 598 public submissions: 595 objections or calls for postponement pending resolution of environmental concerns, two expressions of support and one neutral response. About a third of the submissions came from people living within 200 kilometres of the proposed site, Reuters reported. Because participation was voluntary, these numbers demonstrate the strength of sentiment among respondents rather than the precise views of the wider population.
The timing is striking. Before Anthropic was identified as the project's anchor tenant on September 15, the record showed only five objections over a month. The remainder arrived before submissions closed on November 11. A local planning question had become a much broader debate about who should accommodate the physical infrastructure behind AI.