A landmark order meets a contracting impasse
KHNP said technical discussions, dispute-resolution efforts and executive-level meetings failed to bridge the gap between the two sides. The state operator will prepare a fresh tender. Yonhap reported that the proposed facility includes two Korean-designed APR1000 reactors of 1,000 megawatts each and that the termination of subcontract talks does not cancel the main Czech project.
The argument is partly about price, but not just price. Industry sources cited by The Korea Herald said KHNP had sought a reduction exceeding 10 percent of an earlier construction quotation, representing more than one trillion won. That is a reported negotiating demand, not a confirmed saving or an agreed contractual figure.
Who pays when engineering changes?
KHNP says a fixed-price arrangement is important because its own contract with the Czech customer limits room for overruns. It maintains that it increased proposed compensation for some extra work while challenging items an external review considered excessive, duplicated or incorrectly calculated.