Found in routine inspections
According to an MTR spokesman, routine inspections of incomplete works in October 2026 found that remedial works involving patching materials had been carried out at the heads of columns on the platform level of the Tung Chung West site without the MTR’s prior approval.
The MTR immediately instructed the main contractor to suspend the works concerned and launched an investigation to assess the condition of columns across different zones at the platform and concourse levels, as well as the associated work procedures.
The identified issue does not affect the safety of the completed structure.
Strict requirements for rectification
The MTR set out clear requirements for main contractor Bouygues-Dragages Joint Venture:
- Submit a comprehensive report on the matter along with a proposed rectification plan.
- Resume work only after the MTR and other relevant authorities approve the plan.