When a power pole stops a data centre
Scroggie chose the UBS Australasia conference to deliver the news. Anything without a customer contract and a firm commitment, he said, is no longer a priority. He did not say how many projects would be affected, though the company's 2026 annual report listed 11 centres in development or planning.
The trouble began on suburban streets. Electricity distributor Jemena planned network works to raise supply to M3, including industrial poles about 15 metres high, roughly twice the usual height. Residents protested, in what became known as the wheelie bin revolt, and Jemena suspended parts of the work, citing community and stakeholder opposition. The residents' group Citizens of Tottenham likened the contest to David and Goliath.
"That work can't restart until we clearly communicate that we've solved this problem." Craig Scroggie
The financial cost has been severe. NextDC cut its fiscal 2027 net revenue guidance to between A$475 million and A$500 million, from A$615 million to A$640 million, and Jemena's works are not expected to restart before February 2027. Scroggie has apologised to residents and acknowledged that consultation fell short. He says he has a technical answer to the power problem, yet he knows what it is worth on its own.